14.12.2024

Blows under your feet: in Novosibirsk will start extreme tests of heating systems

“Siberian generating company” announced the beginning of tests on heating systems in Novosibirsk.

“From 23 to 29 may 2018 “Teplovye SETI” of the Novosibirsk branch of “Siberian generating company” for the first time in five years, will conduct tests on the networks for maximum temperature. The purpose of testing is to reveal defects in pipelines, compensators, supports and to verify the compensating ability of heat networks, for which the flow temperature will be raised to 130 degrees.

During the tests, possible washouts, and the release of surface water with temperatures above 100 degrees,” – warn in the GTS.

Upon detection of erosion of soil and water present on the surface of an urgent need to give information on phones:

Горячую воду начнут отключать на следующей неделе

Hot water will be disconnected next week

051 – uniform dispatching service of the city hall;

289-01-47 – shift branch “Heat networks”;

223-17-44 – control office of the 1st district heat networks.

Trials will be held in three stages.

First phase: from 23 to 24 may, the tests of thermal networks on the maximum temperature to be held in the area of heat supply from TPP-5. Under test get heat network October, Railway, Central, Dzerzhinsky, Central and Pervomaisk areas, and also network of the Kirov regional boiler-house and boiler house of the Novosibirsk revocability.

Under test get heat network located:

In Dzerzhinsk area in the street: Aivazovsky, Boris Bogatkova, Brodsky, Vasnetsov, Volga, Volochaevskaya, Gogol, Gusinobrodskoe shosse, Dzerzhinsky prospect Dovatora, Esenin, Comintern, Koshurnikova, Kuprin, Levitan, national, Polzunova, Selezneva, Tolbukhin, Knit, Lazarev, Republican (to the intersection with the Knitted).

In the Railway area on the street: 1905 Burlinskaya, Narym, Siberia, Soviet, Chelyuskintsev, Shamshurina, Vokzalnaya Magistral.

In Zaeltsovsky area on a Linear residential area, street Linear, from the streets Narymsky and Planned towards the river Ob, the street Kropotkin, Kropotkin and Plekhanov zhilmassive, Depot.

In the Oktyabrsky district on the street: Autogenous, Boris Bogatkova, Belinsky, Military, Griboedov Dolidovich, the Danube, Karl Liebknecht, Kirov, Communitiesa, Koshurnikova, archaeology, Leningrad, Leskov, Lobova, Moscow, Nizhny Novgorod, Nikitin, Panfilov, Pedestrian, proletarian, Tolstoy, Turgenev, Chekhov, Shevchenko, Vilyui, Elective, and East housing estate and the Key-Kamyshenskogo plateau.

In the Central district on the streets: Military, Gogol, Poor Damian, Deputy, Derzhavin, Dostoyevsky, Ermak, Ippodromskaya, Kamenskaya, Krylov, Chaplygina, Romanov, Michurin, Nekrasov, Olga Zhilina, October, Ordzhonikidze, Ostrovsky, guerrilla, Pisareva, Family Shamshinykh, Seleznev, Soviet Frunze.

In Pervomaisk the area on the streets: Bauman, Heroes of the Revolution, Red flame, Maria Ulyanova, Marat, day, Pozharsky, Thalmann, Physical, Chapaeva, EICHE.

In the Kirov region on the streets: Shock, Burdenko, Concrete, World, North Zemskomu zhilmassive, Petukhova, Sorge, Gromov, Viktor Mustache, Pallas, Sibiryakov-Gvardeytsev, North passage, Urmanov, Kozhevnikova, Olovozavodsky, Anikina, Concentrating, 20 party Congress, and also Prison to the community.

Second phase: from 25 may to 26 may – in the area of heat supply from CHPP-4.

Under test will be thermal networks, located in Zaeltsovsky, Kalininsky, Dzerzhinsky districts of Novosibirsk on the streets: Aircraft manufacturers, a Teacher, Oleko Dundicha, New dawn, Lazarev, Republican, 25 years of October, Enterprises, Makarenko, Taiga, Alexander Nevsky, Bohdan Khmelnitsky, the people.

In the residential district “Northern bullfinches”: Tayginskiy, Kurchatov, Red dawn, the Dawn Treader. In the district of “Springs”: kochubeya, Springs, Krause, tyulenin, zemnukhova, Svechnikova, Grebenshchikov, Airport, Bardin, Minin, Svetlanov, Cathode, Northern, Spring, Timiryazeva, Vavilov, Country, Perevozchikova, Krasny Prospekt (from Kalinin square to the North), Dmitry Donskoy, Zaleski, Zhukovsky, Dusi Kovalchuk (from a Planned to Zaleski), Planned (even numbers of houses from metrodata to Timiryazev), Tank, Cavalry, New, Gully, Kaunas.

Third phase: from may 28 to may 29 – in the area of heat supply from CHPP-2 (right Bank) and CHP-3. Under test you will get the thermal network in the Leninsky, Oktyabrsky, Railway and Central areas.

In the Leninsky district of the streets: Planning, Kotovsky, mountain and on the descent to the beach at the Oktyabrsky bridge.

In the Oktyabrsky district on the street: Sakko I Vantsetti, Nizhny Novgorod, Garden, Ob, Boris Bogatkova, III internatsionala, Decembrists, Inskaya, Yakushev, rural, Sunrise, Dobrolyubova, Shevchenko.

In the Railway and Central areas on streets: Bolshevist, Factory, Vladimir, Revolution, Shamshurina, Ivacheva, Komsomolsky Prospekt, Prospekt Dimitrova, Vokzal’naya Magistral’, Maxim Gorky, Saltykov-Shchedrin, Omsk, Lenin, Schetinkina, Uritsky, October, Sverdlov, Kolyvanskiy, Kainskaya, serebrennikovskaya, Communist, Soviet, Chaplygin.

This year the heating season will end on may 21. Last year the heating season ended on may 10, and testing of heating systems began may 15.

Добавить комментарий

Ваш адрес email не будет опубликован. Обязательные поля помечены *